Detroit-Windsor Tunnel to close for construction beginning Friday, October 20th

Travel through the Detroit-Windsor Tunnel will be interrupted due to closures as the final phase of a $21.6 million renovation continues.

To complete the project, the tunnel will be closed based on the following schedule:

  • Oct. 20-30 – The tunnel will be closed from 8 p.m. Oct. 20 through 5:30 a.m. Oct 30.
  • Oct. 30-Nov. 22: The tunnel will be closed 8 p.m.-5:30 a.m. Sundays-Thursdays.
  • Nov. 23-26: The tunnel will be open to traffic.
  • Nov. 27-Dec. 23: The tunnel will be closed 8 p.m.- 5:30 a.m. Sundays-Thursdays.
  • Dec. 23- Jan. 1: The tunnel will be open to traffic.
  • Jan. 2- mid-June: The tunnel will be closed from 8 p.m.- 5:30 a.m. Sundays-Thursdays.

The renovations are scheduled for completion in June 2018.